An International Prestart Insurance Survey at Changjiang NPP, China

Tue, Apr 7, 2015

An International Prestart Insurance Survey at Changjiang NPP, which is under construction, was held 3-5 February, 2015 (Changjiang NPP, Tangxing Village of Haiwei Township in the province of Hainan).

The representatives of International pooling system participated in the Survey:

Nuclear Safety, Operations & Third-Party Liability (NSO TPL):

  • Ms. Jiang Ping, China Pool (Team Leader)
  • Mr. Michel de Monval, French Pool

Machinery Breakdown:

  • Mr. Li Zhe, China Pool

Fire Protection:

  • Mr. Sergey Babenko, RANI
  • Mr. An Jiangtao, China Pool (Observer)

The main goal of the Inspection was:

  • To assess insurance risks of Changjiang NPP in order to arrange nuclear third party and MD insurance cover
  • To survey the main facilities, equipment and systems at NPP and to assess their readiness for nuclear reactor start-up
  • To discuss and analyze current operating safety level of the equipment and systems at NPP as well as the fire safety level

The experts appreciated the safety level at NPP and high level of readiness for the process of commissioning.

Following the results of the inspection the experts presented preliminary observations and recommendations, which in accordance with standard procedure will be forwarded to the leaders of Changjiang NPP as soon as the Survey report is finalized.

The inspectors thanked the staff of Changjiang NPP and China National Nuclear Corporation, the owner of the NPP, for the high level of organization of the Survey.

For your information:

The plant will be built in two phases, both consisting of two CNP-600 pressurized water reactors, with a capacity of 650 megawatts each. The first unit is scheduled to be operational by 2015 and second unit by 2016.